Fish Passage Case Studies

Storm Creek
Culvert Replacement Stream Simulation

Case Study Contributor

  • Mark Johnson, Engineer Nez Perce Tribe, Lapwai, Idaho USA
  • Nick Gerhardt, Nez Perce National Forest, Grangeville, Idaho

Location
Tributary to Meadow Creek
South Fork Clearwater River Watershed, Idaho, USA MAP

Project Type

  • Bottomless steel arch culvert on concrete stem wall footings
  • Stream simulation channel bed

Pre-Project Conditions and Barriers

  • Circular CMP 84 in (2.1 m) diameter, 140 ft (43 m) long, at 6.2% slope with small outlet drop
  • Culvert width severely constricted streamflow during sustained high flows supplied by spring snowmelt
  • Excessive drop and velocity barrier for adult and juvenile spring/summer Chinook salmon, cutthroat and steelhead trout

Watershed and Channel Characteristics

  • Drainage Area: 1.9 mi2 (4.9 km2)
  • Peak (100-year) design flow: 89.7 cfs (2.5 cms)
  • Fish passage (2-year) design flow: 23.7 cfs (0.7 cms)
  • Bankfull Width: 12.5 ft (3.2 m)
  • Rosgen Type A3, riffle-pool with narrow valley width

Ecological Value

  • 2.0 mi (3.2 km) of spawning and rearing habitat for steelhead trout, spring/summer Chinook salmon and cutthroat trout
  • Substantial reduction in risk of crossing failure and delivery of fillslope material to downstream spawning habitat

Project Characteristics

  • Open bottom structural steel plate arch culvert on concrete stem wall footings
  • 15 ft (4.6 m) span, 7.75 ft (2.4 m) rise, 108 ft (33 m) length
  • Bed and footing slope: 6.56%
  • Designed for bankfull width plus 2 ft (0.6 m)
  • Sized for conveyance of 100-year flow with associated debris and sediment without overtopping inlet
  • Excavation of 26 vertical feet (8 m) of road fill to install new culvert

Challenges

  • Excavation of large fill volume over crossing took longer than anticipated, made stockpiling of material challenging, and severely limited site access for equipment
  • Bedrock ledge at footing elevation required field redesign of cast-in-placed footing to minimize bedrock removal

Project Contributors

  • Nez Perce Tribe, Lapwai, Idaho
  • Nez Perce National Forest, Grangeville, Idaho

Project Funding

  • Bonneville Power Administration
  • Pacific Coastal Salmon Recovery Fund
  • US Forest Service

Completion Date
September 2006

Project Cost (2006)

Construction $ 192,309
Engineering & Design $ 12,000

Total $ 204,309


Project Summary

The Nez Perce Tribe and the Nez Perce National Forest have been working together to fund replacement of barrier culverts since 2003. This watershed restoration effort includes road decommissioning, soil restoration, and barrier removals.

This project replaced an existing 7 ft (2.1m) x 140 ft (43 m) CMP with a 15 ft (4.5 m) span x 108 ft (33 m) open bottom structural steel plated arch pipe on concrete stem wall footings. A natural stream channel with a slope of 6.6% was constructed through the new crossing using native streambed material from the site mixed with larger rock. The channel inside the culvert included a well defined active channel and streambanks. The bed mixture included fine material to minimize porosity and maintain surface flow. The banks also provided a pathway for smaller terrestrial animals that travel along the riparian corridor; allowing them to migrate through the culvert rather than crossing over the large fill and roadway. A rock vortex weir was constructed upstream of the culvert inlet for grade control to minimize headcutting.

The crossing is located along a sharp switchback in the road within a narrow valley and has a 26 ft (8 m) high fill above the culvert. Excavation of this extremely large amount of fill required working with steep embankments that made equipment access difficult. A concrete pump truck and a crane positioned on the road were used to pour footings and lower materials.

This new crossing allows passage for all aquatic organisms. Native spring/summer Chinook salmon, steelhead and cutthroat trout are now able to access upstream spawning and rearing habitat that was blocked by the old culvert. The new culvert also allows the crossing to pass flood flows and larger debris, reducing the risk of road failure and sediment delivery to important steelhead and salmon spawning habitat downstream.

Post Project Observations and Lessons Learned

The extremely large fill volume took longer to excavate than was estimated. Space for storing the fill material was limited and resulted in steep side slopes creating access problems to the streambed.

A substantial bedrock shelf was found at the footing depth. The contract called for cast-in-place footings and stem walls which were modified in the field to reduce the amount of bedrock to be removed using a rock hammer. Construction using precast footings would have been much more costly at this site, requiring the removal of several feet of bedrock to reach subgrade design depths. A geotechnical investigation that included borings may have alerted designers to the subsurface conditions.

Post construction monitoring shows little change in the site profile or cross sections, suggesting the new channel is stable and functioning as intended. The upstream weir and several boulders placed in the culvert have created resting area and pools throughout the length of the new culvert for use by migrating fish. Post construction planting included native grass seed mix and native shrubs and trees on the new cut slopes which have helped control erosion and will provide shade and slope stability.



Published 05/27/08